| Fear-inspiring candlestick maker | 01/17/18 | | Carmine stage | 01/17/18 | | clear hospital mental disorder | 01/17/18 | | Razzle-dazzle Sadistic Deer Antler Nursing Home | 01/17/18 | | canary old irish cottage | 01/17/18 | | Wild market love of her life | 01/17/18 | | passionate trust fund | 01/17/18 | | Mewling poppy mad cow disease | 01/17/18 | | slap-happy whorehouse | 12/22/25 | | slap-happy whorehouse | 12/23/25 | | slap-happy whorehouse | 12/28/25 | | slap-happy whorehouse | 12/29/25 | | slap-happy whorehouse | 12/29/25 | | slap-happy whorehouse | 01/04/26 | | slap-happy whorehouse | 01/06/26 | | slap-happy whorehouse | 12/22/25 | | vigorous stag film | 01/04/26 | | Diverse Pozpig Sneaky Criminal | 01/04/26 | | slap-happy whorehouse | 01/04/26 | | Talking kitty | 01/04/26 |
Poast new message in this thread
Date: January 17th, 2018 9:52 AM Author: Fear-inspiring candlestick maker
http://www.latimes.com/local/california/la-me-bullet-train-cost-overrun-20180116-story,amp.html
The estimated cost of building 119 miles of bullet train track in the Central Valley has jumped to $10.6 billion, an increase of $2.8 billion from the current budget and up from about $6 billion originally.
The new calculation takes into account a number of intractable problems encountered by the state rail agency. It raises profoundly difficult questions about how the state will complete what is considered the nation’s largest infrastructure project with the existing funding sources.
The new estimate was presented Tuesday by Roy Hill, who leads the main consulting firm on the project, WSP (formerly Parson Brinckerhoff). Hill said the cost increases were mainly driven by problems including higher costs for land acquisition, issues in relocating utility systems, the need for safety barriers where the bullet trains would operate near freight lines and demands by stakeholders for the mitigation of myriad issues.
“The worst-case scenario has happened,” Hill bluntly told the rail authority’s board at its regular monthly meeting.